Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach

Robert H. Doersch, James H. Patterson

Management Science · 1977 · Volume 23 · Issue 8

DOI: 10.1287/mnsc.23.8.882

Abstract

A zero-one integer programming formulation of the project scheduling problem is reported which maximizes the discounted value of cash flows in a project when progress payments and cash outflows are made upon the completion of certain activities. While this problem has been treated previously, it has not been addressed in a manner which allows for the type of constraints treated in this paper. And while cash can be treated as any other resource in the noncash flow, resource-constrained version of this problem, the effects of cash inflows and outflows and the time sequencing alternatives for them allow for a different treatment of cash resources than has been previously reported.