A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions

Robert A. Russell

Management Science · 1986 · Volume 32 · Issue 10

DOI: 10.1287/mnsc.32.10.1291

Abstract

The problem addressed in this paper is the scheduling of activities in a project to maximize net present value given cash inflows, outflows, and resource restrictions. Although optimization procedures exist for small problems of this type, they generally cannot solve large-scale problems and may not be widely available. Six heuristic scheduling rules are compared on 80 test problems. The test problems include large-scale engineering construction projects as well as 50 resource constrained problems from the literature.

Keywords

project management: resource constraints, finance: capital rationing, industries: construction